PROJECT CASE STUDY
·
#631200
Decontamination and Fluid Purification on Two EHC Hydraulic Systems
FINAL
System 1 On-Site ISO Count: 12/8/0
SNAPSHOT
ASSET(S)
Two EHC Hydraulic Systems
YEAR
2026
OBJECTIVE
WHAT WE FOUND
HOW WE DID IT
PROCESS
Mobilize equipment and set up after gaining site access.
Start slip-stream purification on System 1 and cycle the system to return oil to its reservoir.
Measure the initial particle count, then repeat purification and monitor particle counts in real time.
Repeat purification and monitoring on System 2.
Record final on-site counts and release both systems for commissioning.
TECHNICAL DETAILS
VERIFICATION METHOD
Real-time ISO 4406:1999 laser particle counting. Independent laboratory results are provided separately in the PDF appendix.
FLUID
Existing Hydraulic Oil
FLUID VOLUME
35 USG Capacity per System
RELEVANT SPECIFICATIONS
Two EHC hydraulic systems. The team cycled each system to return oil to the reservoir for repeated slip-stream purification.
THE NUMBERS
System 1 On-Site ISO Count
18/17/9
→
12/8/0
TARGET:
16/14/11 or Better
System 2 On-Site ISO Count
18/15/11
→
12/11/10
TARGET:
16/14/11 or Better
SAFETY
100% Safety Record
Every Step. Every Reading.
This page is the short version. The full report walks through every step we took, how we verified it, and what the numbers came back at. Customer details are redacted. The data isn’t.
Download Full Technical Report
MORE WORK FROM THE FIELD
ISO Particle Count: 14/11/7
Chemical Clean and Oil Flush on Two Boiler Feedwater Pump Lube Oil Systems
Main NAS Rating: NAS 5
Chemical Clean and Oil Flush on Main and Auxiliary Hydraulic Power Units
ISO Particle Count: 14/12/8